A ninety day lead time is a ninety day currency position

The exchange rate that matters is the one on the day of payment, and the purchase order is placed months before that day. Between the two sits an exposure that most buyers discover only when the margin has already gone.

The exchange rate that matters is the one on the day of payment, and the purchase orde
Plate 08 · currency · Cargo Cost Notes

The exposure is the gap between order and payment

A purchase order priced in a foreign currency creates an obligation to pay a fixed amount of that currency at a future date. The home currency cost of that obligation moves with the rate until the payment is made.

The exposure therefore begins at the moment the price is fixed and ends at the moment the payment clears. A ninety day lead time plus thirty day payment terms is a hundred and twenty day exposure, not a ninety day one.

The size of the exposure is the foreign currency amount multiplied by the possible rate movement. That product is the amount at risk, and it is computable before the order is placed rather than after the invoice arrives.

The margin on the order is the natural limit on the exposure. An order with a thin margin cannot absorb much rate movement, and the exposure should be measured against the margin rather than against the order value.

Who bears the risk is a contract term

The currency of the price decides who bears the risk. A price in the seller's currency puts the risk on the buyer. A price in the buyer's currency puts it on the seller, who will price that risk into the quotation.

The seller's pricing of the risk is usually a cushion rather than a hedge, which means it is an average rather than a precise figure. A buyer that accepts a home currency price is paying the average cushion and keeping no upside.

A third option is a price in a third currency that both parties regard as neutral, which is common in commodity trade. The risk is then shared in the sense that neither party's home currency is the reference.

The choice is a negotiation and it should be made with the exposure size known. A buyer that asks for its own currency without knowing the cushion it is paying is negotiating blind.

Natural hedging comes first

A business that earns in one currency and pays in the same currency has a natural hedge, because the foreign currency inflow covers the outflow. Related party structures often create this automatically.

A business that earns at home and pays abroad has no natural hedge and must hedge financially or accept the exposure. A business that sells abroad in the same currency it buys in has a partial hedge that varies with the volume match.

The volume match is the variable that matters. A company that buys a large amount in a currency and sells a small amount in the same currency is hedged on the small amount and exposed on the remainder.

The natural hedge should be measured before any instrument is bought, because instruments cost money and a natural hedge costs nothing. Most over hedging starts with a failure to net the flows.

Forwards and options cost differently

A forward fixes the rate for a future date. It removes the uncertainty and it removes the upside, and it carries a credit exposure to the bank between trade date and settlement.

An option gives the right to transact at a rate without the obligation. It preserves the upside and it costs a premium, and the premium is usually large enough to be a visible line in the order's margin.

The choice between them depends on whether the business can absorb the upside loss. A business that has quoted a fixed price to its customer has no upside to preserve, so a forward is appropriate. A business that will reprice has upside and may prefer an option.

A third instrument is a collar, which combines a bought and a sold option to reduce the premium at the cost of a capped upside. Collars are attractive in thin margin businesses and they carry a risk if the rate moves beyond the cap.

Hedging the layers of a payment schedule

A purchase order paid in instalments has several exposures rather than one, because each instalment settles on its own date. A single forward for the total covers the average and leaves each instalment imperfectly matched.

The correct structure is a strip of forwards or options, one per instalment date, each sized to the instalment. The strip is more work to arrange and it produces a hedge that matches the cash flow.

A deposit paid at order placement is an exposure with a very short horizon and it is often overlooked because it happens at the start. A deposit in foreign currency is a foreign currency payment whether or not goods have shipped.

The practice is to list the payment dates from the contract and hedge each one, rather than to hedge the total on the assumption it will be paid at the midpoint.

Adjustment clauses shift the exposure back

A price adjustment clause allows the price to move with the rate beyond a stated band. The seller is protected beyond the band and the buyer keeps the movement within it.

The clause is a sharing mechanism and it should be symmetric where the negotiation allows. A one sided clause protects one party and is priced by the other, usually as a higher base price.

The band should be set from the observed volatility rather than from a round number. A band that is too narrow triggers frequent renegotiation, and a band that is too wide protects nobody.

The clause needs a reference rate, a reference date and a calculation method stated in the contract. A clause that says the price will be adjusted for currency movements without those three is a clause that produces a dispute rather than a protection.

The rate in the quotation

A quotation in a foreign currency embeds an assumed rate. If the assumption is the spot rate on the day of quotation, the quotation is wrong for every order that settles later.

The assumption should be a forward rate for the expected payment date, or the spot rate plus a stated cushion. Either is defensible and both should be written down, so that the margin can be reconstructed later.

The cushion should be sized to the exposure and to the margin. A cushion large enough to absorb the expected movement is a cushion that makes the quotation uncompetitive, so the trade off should be explicit rather than accidental.

The assumption should be recorded per quotation and reviewed when it is older than the volatility horizon. A quotation built on a rate from six months ago is a quotation built on a rate that no longer exists.

The accounting that hides the exposure

A purchase in foreign currency is recorded at the rate on the transaction date and remeasured at the rate on the reporting date. The remeasurement produces an exchange difference that appears in the accounts before the cash moves.

That difference is a real economic exposure reported as an accounting one, and it can be large enough to distort a period's result. It is also the number that makes the exposure visible to a finance team that does not see the purchase orders.

Hedge accounting is the mechanism that lets a hedge's gain or loss be recognised alongside the item it hedges. Without it the hedge appears as a separate volatile line, which discourages hedging for presentation reasons rather than economic ones.

The practical point is that the accounting treatment should not decide the hedging policy. A business that does not hedge because the accounting is awkward has chosen presentation over margin.

Concentration and the counterparty

A hedging programme concentrates exposure in a bank rather than eliminating it. The forward is only as good as the bank's performance, and the bank's exposure to the business is a credit line that has to be in place.

The credit line is the practical constraint on hedging for small and medium importers. A bank will not write forwards beyond a credit limit, and the limit is sized to the trading relationship rather than to the exposure.

Where the credit line is insufficient, the alternatives are a smaller hedge ratio, a longer banking relationship or an instrument that requires collateral instead of credit.

The hedge ratio itself should be a policy number rather than a per order judgement. A stated ratio applied consistently produces a predictable result and avoids the pattern of hedging after the rate has moved.

The rule that fits a long lead time

The rule: measure the exposure from order date to payment date, net the natural flows, hedge a stated ratio of the residual as a strip matched to the payment schedule, and record the assumed rate in every quotation.

The rule should also state the review trigger: a movement beyond the band in an adjustment clause, a change in the payment schedule, or a change in the currency of a major supplier. Those three are the events that invalidate a hedge.

And it should state who owns the residual exposure. Some residual is deliberate, because a hedge ratio below one is a decision to keep some upside. That residual should be named and sized rather than left as a remainder.

A rule with a measurement, a netting step, a ratio, a schedule and an owner is a currency policy. Anything less is a habit, and a habit is what produces the margin loss that nobody can explain in the quarterly review.

The exposure this note measures is set out in currency risk on long lead purchase orders, where the position runs from the purchase order date rather than from the shipment.

Resolving notes12 points
  • Measure the exposure from order date to payment date, not from shipment.
  • Size the exposure against the order margin rather than against the order value.
  • Net natural inflows and outflows in the same currency before buying any instrument.
  • Choose between forward and option by whether the business has upside to preserve.
  • Hedge each instalment date separately rather than the total at a midpoint.
  • Treat a foreign currency deposit at order placement as an exposure in its own right.
  • Make adjustment clauses symmetric with a stated band, reference rate and date.
  • Quote from a forward rate or a spot rate plus a written cushion, never spot alone.
  • Record the assumed rate per quotation and review it when it ages.
  • Do not let hedge accounting presentation decide the hedging policy.
  • Confirm the bank credit line before committing to a hedge ratio.
  • State a hedge ratio as policy and name who owns the deliberate residual.